Shutdown of all systems on 2 february at 07:00 CET closed
The UPPMAX compute hall will be partially shutdown during 2 February between 07:00 - 11:00 CET as Akademiska Hus performs work on the cooling circuit. The shutdown has been planned to coincide with our February maintenance day. We will try to provide some level of access but expect all compute capability to be unavailable until the work is completed.
If you have any questions please contact us at support@uppmax.uu.se.
Best regards, UPPMAX
Update 2022-02-02 06:00
Shutdown has started. We expect all systems to be offline by 07:00 CET.
Update 2022-02-02 07:14
All systems are shutdown.
Update 2022-02-02 11:00
The cooling system maintenance outside of our datacenter is more time-consuming than expected. It is unlikely that we will be able to resume operations today.
Update 2022-02-02 15:50
Cooling system maintenance completed. Compute hall is back to normal temperatures. We will now start restoring services and systems starting with internal infrastructure.
Update 2022-02-03 13:45
The cooling shutdown is complete and we will continue working with the February maintenance window with updates of all our services. This ticket will be closed.